Extremely Detailed Calendar

Due Thursday - extremely detailed calendar. do all days, not just class meeting days. (123 total shots)

Oct. 5 - 70% of assets completed at this point.
Oct. 6 - 80% of assets completed. (Work schedule 10-7. School work completed after 7)
Oct. 7 - 100% of assets completed. Miscellaneous assets imported into AE. Rigging completed for ones that need it for shots 1-6.
Oct. 8 - Character assets and backgrounds imported into AE, rigged, staged for shots 1-6. (Work schedule 10-7. School work completed after 7)
Oct. 9 - Close-up assets (hands/tentacles/etc.) staged and motion tested for shots 1-6. (Work schedule 1-10. School work completed before 1)
Oct. 10 - Character motion tests for shots 1-6.(Meeting from 5-10. School work completed before 5)
Oct. 11 - Tweaking and editing assets/staging for shots 1-6. (Work schedule 10-7. School work completed after 7)
Oct. 12 - Mid-Term Grading - Begin animation - shots 1 through 4.
Oct. 13 - (Work schedule 10-7) Animation shots 5 and 6.
Oct. 14 - Mid-Term Grading Animation and staging shots 7 - 10.
Oct. 15 - (Work schedule 10-7) Animation shots and staging 11-14.
Oct. 16 - Animation and staging shots 15-18.
Oct. 17 - Animation and staging shots 19-21.
Oct. 18 - Fall Break
Oct. 19 - Fall Break
Oct. 20 - Animation and staging shots 22-26, 27-31.
Oct. 21 - Animation and staging shots 32-36, 37-41.
Oct. 22 - Realistically, I will be out of town. On work business. So there really won't be time for working on this. Due to this, I'm assuming responsibility for doing these 3 days of work PRIOR to leaving.
Oct. 23 - Realistically, I will be out of town. On work business. So there really won't be time for working on this. Due to this, I'm assuming responsibility for doing these 3 days of work PRIOR to leaving.
Oct. 24 - Realistically, I will be out of town. On work business. So there really won't be time for working on this. Due to this, I'm assuming responsibility for doing these 3 days of work PRIOR to leaving.
Oct. 25 - Animation and staging shots 42-46.
Oct. 26 - Revise/edit previous shots.
Oct. 27 - Animation and staging shots 47-51.
Oct. 28 - Revise/edit previous shots.
Oct. 29 - Animation and staging shots 52-56.
Oct. 30 - Revise/edit previous shots.
Oct. 31 - Animation and staging shots 57-61.
Nov. 1 - Revise/edit previous shots.
Nov. 2 - Animation and staging shots 62-66.
Nov. 3 - Revise/edit previous shots.
Nov. 4 - Animation and staging shots 67-71.
Nov. 5 - Revise/edit previous shots.
Nov. 6 - Animation and staging shots 72-76.
Nov. 7 - Revise/edit previous shots.
Nov. 8 - Animation and staging shots 77-81.
Nov. 9 - Revise/edit previous shots.
Nov. 10 - Animation and staging shots 82-86.
Nov. 11 - Revise/edit previous shots.
Nov. 12 - Animation and staging shots 87-91.
Nov. 13 - Revise/edit previous shots.
Nov. 14 - Animation and staging shots 92-96.
Nov. 15 - Revise/edit previous shots.
Nov. 16 - Animation and staging shots 97-101.
Nov. 17 - Revise/edit previous shots.
Nov. 18 - Animation and staging shots 102-106.
Nov. 19 - Revise/edit previous shots.
Nov. 20 - Animation and staging shots 107-111.
Nov. 21 - Revise/edit previous shots.
Nov. 22 - Animation and staging shots 112-116.
Nov. 23 - Revise/edit previous shots.
Nov. 24 - Thanksgiving Holiday
Nov. 25 - Thanksgiving Holiday
Nov. 26 - Thanksgiving Holiday
Nov. 27 - Thanksgiving Holiday
Nov. 28 - Thanksgiving Holiday
Nov. 29 - Animation and staging shots 117-123.
Nov. 30 - Revisions to animation.
Dec. 1 - Finish AE tests for presentation.
Dec. 2 - Revisions to animation.
Dec. 3 - Revisions to animation.
Dec. 4 - Revisions to animation.
Dec. 5 - Revisions to animation.
Dec. 6 - Critique and revision.
Dec. 7 - Critique and revision.
Dec. 8 - Critique and revision.
Dec. 9 - It's due.

Even More Assets